CECEP Yangjiang Nanpeng Island 300MW offshore wind power booster station basic project held a groundbreaking ceremony

CECEP Yangjiang Nanpeng Island 300MW offshore wind power booster station basic project held a groundbreaking ceremony

  • Categories:Company News
  • Author:
  • Origin:
  • Time of issue:2019-03-20
  • Views:0

(Summary description)At 10:00 am on March 19, 2019, the groundbreaking ceremony for the foundation jacket and steel pipe pile construction project of the booster station of the 300MW offshore wind power project in Yangjiang Nanpeng Island of CECEP was held as scheduled.

CECEP Yangjiang Nanpeng Island 300MW offshore wind power booster station basic project held a groundbreaking ceremony

(Summary description)At 10:00 am on March 19, 2019, the groundbreaking ceremony for the foundation jacket and steel pipe pile construction project of the booster station of the 300MW offshore wind power project in Yangjiang Nanpeng Island of CECEP was held as scheduled.

  • Categories:Company News
  • Author:
  • Origin:
  • Time of issue:2019-03-20
  • Views:0
Information

At 10:00 am on March 19, 2019, the groundbreaking ceremony for the foundation jacket and steel pipe pile construction project of the booster station of the 300MW offshore wind power project in Yangjiang Nanpeng Island of CECEP was held as scheduled. With Mr. Cheng Dewei from the Construction Department of CECEP Offshore Engineering pressing the control button of the first steel plate blanking and cutting program, the production process of the project officially kicked off. Also present at the groundbreaking ceremony were the main person in charge of the project owner CECEP, the person in charge of the Guangzhou Salvage Bureau of EPC, and the person in charge of the SGS supervision unit. During the period, Zhen Yongpeng, the project manager of Taisheng Landau, presided over the project progress communication meeting and introduced the progress of the project and the coordination matters with related parties to the participants.

CECEP Yangjiang Nanpeng Island 300MW offshore wind power project is located in the sea area south of Nanpeng Island, Dongping Town, Yangjiang City, Guangdong Province. It is a key project in the western Guangdong sea area of ​​Guangdong Province this year. It is also the first booster station for our company’s Guangdong regional offshore wind power business. Infrastructure construction projects.

The main steel structure of the booster station has a total weight of more than 3,100 tons and a jacket height of 45.5 meters, which is equivalent to the height of a 17-story residential building. It is by far the most important offshore wind power booster station jacket in China. The project is scheduled to be delivered to the site in late June this year. The Blue Island Project Department will make full arrangements for efficient implementation and advancement to ensure that the project is delivered on time and with quality.

 

Photo 1: Project progress communication meeting

news

 

Photo 2: The first steel plate counting and cutting program started

news

Scan the QR code to read on your phone

Recommended News

Nantong Taisheng Blue Island Offshore Co., Ltd.

Tel: 

Address:

No.1,Blue Island Road,Marine&Offshore Industrial Park, Qidong City, Jiansu Province. Province