The first batch of 4 steel pipe piles for Xiangshui booster station was completed and delivered

The first batch of 4 steel pipe piles for Xiangshui booster station was completed and delivered

  • Categories:Company News
  • Author:
  • Origin:
  • Time of issue:2015-07-17
  • Views:0

(Summary description)On July 14, the Xiangshui Wind Power Steel Pipe Piles Project undertaken by Nantong Landao Offshore Engineering Co., Ltd. held the first batch of 4 booster station steel pipe piles completion acceptance meeting, Yangtze Three Gorges Technology and Economic Development Co., Ltd., Xiangshui Yangtze River Wind Power Ten representatives from Sanxia Jinjie Inspection Center, CCCC Third Navigation Engineering Bureau Co., Ltd. and relevant leaders of Landao Offshore attended the meeting.

The first batch of 4 steel pipe piles for Xiangshui booster station was completed and delivered

(Summary description)On July 14, the Xiangshui Wind Power Steel Pipe Piles Project undertaken by Nantong Landao Offshore Engineering Co., Ltd. held the first batch of 4 booster station steel pipe piles completion acceptance meeting, Yangtze Three Gorges Technology and Economic Development Co., Ltd., Xiangshui Yangtze River Wind Power Ten representatives from Sanxia Jinjie Inspection Center, CCCC Third Navigation Engineering Bureau Co., Ltd. and relevant leaders of Landao Offshore attended the meeting.

  • Categories:Company News
  • Author:
  • Origin:
  • Time of issue:2015-07-17
  • Views:0
Information

On July 14, the Xiangshui Wind Power Steel Pipe Piles Project undertaken by Nantong Landao Offshore Engineering Co., Ltd. held the first batch of 4 booster station steel pipe piles completion acceptance meeting, Yangtze Three Gorges Technology and Economic Development Co., Ltd., Xiangshui Yangtze River Wind Power Ten representatives from Sanxia Jinjie Inspection Center, CCCC Third Navigation Engineering Bureau Co., Ltd. and relevant leaders of Landao Offshore attended the meeting.

  

news

 

There are 4 steel pipe piles in Xiangshui Boosting Station, each with a length of 68 meters, a diameter of 2-3 meters, and a total weight of 725.87 tons. They have passed the completion acceptance and shipped smoothly. They are expected to arrive at the Xiangshui installation site on July 18. And finally delivered.

 

news

 

news

 

news

 

news

  

The production preparations for the subsequent 9 steel pipe piles of the Xiangshui Wind Power Steel Pipe Pile Project are being carried out in an orderly manner as planned, and construction will be fully started in the near future.

Scan the QR code to read on your phone

Recommended News

Nantong Taisheng Blue Island Offshore Co., Ltd.

Tel: 

Address:

No.1,Blue Island Road,Marine&Offshore Industrial Park, Qidong City, Jiansu Province. Province

Copyright © 2021 Shanghai Taisheng Wind Power Equipment Co.,Ltd.   沪ICP备11022703号