The basic project of the booster station of Jiangsu Dongtai 200MW offshore wind power project only takes one month from start to delivery

The basic project of the booster station of Jiangsu Dongtai 200MW offshore wind power project only takes one month from start to delivery

  • Categories:Company News
  • Author:
  • Origin:
  • Time of issue:2016-05-08
  • Views:0

(Summary description)On March 8th, our plant received the bid-winning notice for the basic engineering of the booster station of Jiangsu Dongtai 200MW offshore wind power project (hereinafter referred to as the Dongtai booster station project), and immediately organized the company’s relevant personnel to hold a meeting on the project.

The basic project of the booster station of Jiangsu Dongtai 200MW offshore wind power project only takes one month from start to delivery

(Summary description)On March 8th, our plant received the bid-winning notice for the basic engineering of the booster station of Jiangsu Dongtai 200MW offshore wind power project (hereinafter referred to as the Dongtai booster station project), and immediately organized the company’s relevant personnel to hold a meeting on the project.

  • Categories:Company News
  • Author:
  • Origin:
  • Time of issue:2016-05-08
  • Views:0
Information

On March 8th, our plant received the bid-winning notice for the basic engineering of the booster station of Jiangsu Dongtai 200MW offshore wind power project (hereinafter referred to as the Dongtai booster station project), and immediately organized the company’s relevant personnel to hold a meeting on the project. A preliminary assessment and understanding of the difficulties and risks of the company. This project includes a jacket (756 tons) and four steel pipe piles (total 648 tons) and is required to be delivered to the Dongtai construction site before April 30.

 

news

 

On the premise of the arrival of the relevant steel products, our company officially started the project on March 30. In the meantime, due to the weather caused a greater impact on the production plan, our factory organized multiple technical meetings and made in-depth adjustments to the production plan to avoid the possible impact due to weather, so as to complete the Dongtai upgrade on time and maintain the quality. Press station project. Of course, the construction team that integrates combat effectiveness and experience is even more indispensable, as well as strong equipment logistics support. In the end, with the collective efforts of the entire company, the jacket was completed on April 27 and arrived at the construction site in Dongtai on the 29th of the same month.

 

news

 

On May 07, the company held a summary meeting on the Dongtai booster station project. In view of the difficulties and risks in the project, the meeting made a further summary, and made a comprehensive analysis of its own strengths and weaknesses. While putting forward relevant improvement requirements for each department, it also required each department to list specific matters as a code of conduct , In order to achieve faster, more stable and more accurate in future projects, so as to achieve the company's strategic goal of sustainable development and avoid the phenomenon of catching fish.

Scan the QR code to read on your phone

Recommended News

Nantong Taisheng Blue Island Offshore Co., Ltd.

Tel: 

Address:

No.1,Blue Island Road,Marine&Offshore Industrial Park, Qidong City, Jiansu Province. Province

Copyright © 2021 Shanghai Taisheng Wind Power Equipment Co.,Ltd.   沪ICP备11022703号