The kick-off meeting for the construction of the booster station project of the H3 offshore wind farm in Binhai South of China Power Investment Corporation was successfully held

The kick-off meeting for the construction of the booster station project of the H3 offshore wind farm in Binhai South of China Power Investment Corporation was successfully held

  • Categories:Company News
  • Author:
  • Origin:
  • Time of issue:2019-03-12
  • Views:0

(Summary description)At 13:00 pm on March 8, 2019, the technical communication and project kick-off meeting for the construction project of the booster station of the 300MW offshore wind farm in Binhainan H3# of Guodian Investment was held as scheduled in Taisheng Landau. Participants in the meeting were the owner State Power Investment Jiangsu Offshore Wind Power, China Power Investment Engineering Company, the engineering design party Huakan Institute, the engineering supervision party Huadong Consulting, and the relevant persons in charge of CCS Classification Society.

The kick-off meeting for the construction of the booster station project of the H3 offshore wind farm in Binhai South of China Power Investment Corporation was successfully held

(Summary description)At 13:00 pm on March 8, 2019, the technical communication and project kick-off meeting for the construction project of the booster station of the 300MW offshore wind farm in Binhainan H3# of Guodian Investment was held as scheduled in Taisheng Landau. Participants in the meeting were the owner State Power Investment Jiangsu Offshore Wind Power, China Power Investment Engineering Company, the engineering design party Huakan Institute, the engineering supervision party Huadong Consulting, and the relevant persons in charge of CCS Classification Society.

  • Categories:Company News
  • Author:
  • Origin:
  • Time of issue:2019-03-12
  • Views:0
Information

At 13:00 pm on March 8, 2019, the technical communication and project kick-off meeting for the construction project of the booster station of the 300MW offshore wind farm in Binhainan H3# of Guodian Investment was held as scheduled in Taisheng Landau. Participants in the meeting were the owner State Power Investment Jiangsu Offshore Wind Power, China Power Investment Engineering Company, the engineering design party Huakan Institute, the engineering supervision party Huadong Consulting, and the relevant persons in charge of CCS Classification Society. The meeting was presided over by Mr. Pan Siwei, executive vice president of Taisheng Landau, and the company's project, technology, quality, production and other functional leaders attended the meeting.

Mr. Zhu Ruijun, deputy general manager of the owner, State Power Investment Corporation Jiangsu Offshore Wind Power Company, first spoke highly of the technology, quality, and progress of the Binhai North H2 booster station and Dafeng H3 booster station that have been successfully delivered by Taisheng Landau. Recognition, and at the same time expressed expectations and confidence in the innovation and excellence of the project. The project team members of the company had a thorough discussion with the responsible engineer of the Huakan Institute in charge of the project, the owner's engineering company, and the project supervisor, and finally formed a project implementation memorandum, requesting the project team to start and implement it as soon as possible.

Guodian Investment Binhai H3 booster station is jointly designed by British ATKINS and Huakan Institute, which accommodates the world's top ocean booster station design, operation and maintenance technology. Its internal structure has been systematically and locally optimized on the basis of the original design, which further improves the utilization of structural space layout; the upgrade of the safety emergency system further provides guarantee for the safety of wind farm operation and maintenance; the project innovatively adopts pile shoe ducts The structure of the foundation of the frame booster station improves the efficiency of the installation and construction process. The smooth start of the project marks that Taisheng Landau has officially entered the field of offshore wind power high-end technology construction!

 

news

Scan the QR code to read on your phone

Recommended News

Nantong Taisheng Blue Island Offshore Co., Ltd.

Tel: 

Address:

No.1,Blue Island Road,Marine&Offshore Industrial Park, Qidong City, Jiansu Province. Province

Copyright © 2021 Shanghai Taisheng Wind Power Equipment Co.,Ltd.   沪ICP备11022703号